ZYNE Schedule Briefing

Posted 07/31/2026

Repair Schedule

Tentative repair schedule for property safety, systems, interior, exterior, and final repair work from August 2026 through July 2029.

This tentative schedule organizes repair work by phase, work description, and expected timeframe. Timing may be refined as work is coordinated.

Tentative repair schedule

Phased repair timeline

Living room ceiling fan and interior baseline condition at 7101 Wendemere St

Phase 1

Safety & Baseline

August - September 2026
  • Replace and test all security devices/detectors
  • Check ceiling fans in bedroom/living room
  • HVAC and water heater checkup
  • Kitchen and toilet plumbing checked
  • Switch plates, outlet covers, etc. checked
  • Front and back doors fixed with new hardware
  • One-time mow the grass
  • Initiate quarterly pest control
Rear exterior and yard view showing foundation and exterior systems context at 7101 Wendemere St

Phase 2

Structural & Systems

October 2026 - April 2027
  • Check and fix subfloor
Kitchen interior showing plumbing, outlet, door, flooring, and wall finish context at 7101 Wendemere St

Phase 3

Interior Cosmetics & Comfort

May - November 2027
  • Drywall cover-up in utility room
  • Sheetrock and drywall cover-up/replacement
  • All inside doors fixed or replaced
  • Insulate subfloor
Front yard, mailbox, fence, and exterior approach at 7101 Wendemere St

Phase 4

Exterior & Low-Priority

December 2027 - May 2029
  • All outside lighting checked
  • Exterior building paint
  • Broken bedroom window replaced (cosmetic)
  • Broken fence repaired (cosmetic)
Cropped front yard view showing the mailbox and carport approach at 7101 Wendemere St

Phase 5

Final Touches

June - July 2029
  • Mailbox repaired
  • Sand fill the carport

Schedule notes

Planning assumptions